The document that is proof of upper management’s commitment to the project & gives the authority to manage the project to the PM is called: ?

a. The project plan b. The project goals and objectives c. The project charter d. The project definition

user-image
Question added by Richa Tiwari , Quantity Surveyor , Space Contracting Limited
Date Posted: 2018/12/26
Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

The project charter is the document that proof of upper management commitment to the project and gives the authority to manage the project to PM.