Register now or log in to join your professional community.
A. Performance measurement analysis B. Forecasting, variance management C. Cost change control system D. Cost aggregation E. Project performance reviews
Correct Answer is D.:Cost aggregation
I think Cost aggregating, through project management, using the tool of Control Estimates, will be the least, plus other choices available.
D. Cost aggregation - all other choices are helpful tool/ technique in the process.
D. Cost aggregation
THE ANSWER
D. Cost aggregation
D. Cost aggregation ........
D. Cost aggregation ------------------
The least one tool or technique for cost controller is (B.) Forecasting and Variance Management. Variance calculation provides knowledge of overspending of major KPI´s with respect to the cost baseline. Moreover, the forecasting allows management to know the impact on the overall project and initiate thoughts for the mitigation and recovery measurements.