Deflection or transfer of a risk to another party is part of which of the following risk response categories?

A. Mitigation B. Acceptance C. Avoidance D. Analysis

user-image
Question added by Zakir Muhammed , Contract Administrator , DS Contracting Co.
Date Posted: 2019/01/05
osama khalifa
by osama khalifa , sourcing manager , Toshiba

Risk Avoidance is close to be the right one

Obaid ur Rehman
by Obaid ur Rehman , HR Executive , Al Bahr Al Arabi Marine Engineering Services

i think that correct Answer is A: Mitigation

saleem abrar
by saleem abrar , Recruitment Coordinator (Client Management & Recruitment) , HABSONS JOBUPS LIMITED

The choices of response strategies for THREATS include:

AVOID: Focus on eliminating the cause and thus, eliminating the threat.

MITIGATE: There are certain risks that cannot be eliminated. However, their impact can be reduced. This is termed as mitigation of risks.

TRANSFER: Transfer the risk to some other party. Insurance purchases, warranties, guarantees, etc are examples of risk transfers.

Nasiru Ahmed bunkure
by Nasiru Ahmed bunkure , Executive Director , 08038498837

Deflection or transfer of a risk party is called transference and it normally occur in project managements.other method are Acepting risk,avoiding risk and mitigatios.and other types of risk include market,Credit,Liquidity and operational risk

MURAT MIDIK
by MURAT MIDIK , SAP Project Manager , Spectrum Consulting

Correct Answer is A: Mitigation

Al Amin  Hossain
by Al Amin Hossain , SrExecutive Accounts , Ariz Technologies Ltd

 

Deflection or transfer of a risk to another party is part of which of the following risk response categories

  Mitigation

CA Radhakrishnan Kadunganattil
by CA Radhakrishnan Kadunganattil , Finance Manager (Head of Finance) , Abdulla Al Rostamani Properties LLC

Transer of risk to another party is a case of risk mitigation. For eg taking insurance cover will not avoid the risk but it will definitely mitigage the risk in case of an untoward incident. 

Risk avoidance is relevant when the risk is completely avaoided. For eg to avoid a particular risk business had decided not to pursue with the project. Here the risk is completed avoided.

 

Mohammed Qaisar I PMP I MCIPS I MBA
by Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

From the given options I feel mitigation is the best suiting answer. Last three options are purely irrelevant.  Transfer of risk to another party may be done by means of following some options, like assigning particular work to the third part, taking insurance, warranties & guarantees etc.  

Fuzail patankar
by Fuzail patankar , Procurement Manager , sss international fze

The most favored answer is C - Avoidance

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

I think that question is not clear because there are four risk response and one of them is transfer. I think the best option as given above is mitigation in this scenario because acceptance and avoidance is irrelevent option.

Zakir Muhammed
by Zakir Muhammed , Contract Administrator , DS Contracting Co.

Mitigation is the correct answer..