Which of the following statements are false regarding the close project process?

A. The output of the close project includes two procedures: administrative closure procedure and contract closure procedure B. The close project process establishes the procedures to verify and document the project deliverables C. The close project process is necessary for managing the contract and relationship between the buyer and seller D. In multi-phase projects, the close project process closes out the associated activities applicable to a given project phase E. The close project process documents the reasons for actions taken if a project is terminated early

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/01/09
Massimiliano Valline
by Massimiliano Valline , Head Procurement , itabia sarl

c. is false because the close project process is not managing the contract and the relationship between the buyer and Seller. This Relationship are already sign on Start of the contract.

Kazi  Golam Kibria
by Kazi Golam Kibria , Sr. Engineer, Network & Security , Express Systems Ltd.

My answer is "C" because the realationship between buyer and seller has fixed up before starting the project. So there is no relationship between  close project process and  the contract between buyer and seller.

Ghaith Taraben
by Ghaith Taraben , Head of Mission , Qatar Red Crescent

C: The close project process is necessary for managing the contract and relationship between the buyer and seller IS THE FALSE ANSWER

Deleted user
by Deleted user

B. The close project process establishes the procedures to verufy and document the project deliverables

Syed Abdullah Zubair
by Syed Abdullah Zubair , Associate Business Process Consultant , Y-30 TECHNOLOGY ACES PVT. LTD.

The answer is D in multiphase project you dont have to close the activities 

shahzad mahmood
by shahzad mahmood , Land Surveyor , El-Seif Engineering Contracting co

A. In multi-phase projects, the close project process closes out the associated activities applicable to a given project phaseB. The output of the close project includes two procedures: administrative closure procedure and contract closure procedureC. The close project process is necessary for managing the contract and relationship between the buyer and sellerD. The close project process establishes the procedures to verify and document the project deliverablesE. The close project process documents the reasons for actions taken if a project is terminated early

JorgeAntonioLuìs Lamia
by JorgeAntonioLuìs Lamia , Studies DEGREE MSC ARCHITECTURE

I believe the "C"

JorgeAntonioLuìs

MY Answer is C,is false because the close project process is not managing the contract and the relationship between the buyer and Seller. This Relationship are already sign on Start of the contract.

mohd kamran
by mohd kamran , Project Manager , Turner & Townsend

C. The close project process is necessary for managing the contract and relationship between the buyer and seller 

Deleted user
by Deleted user

I think its "C"

C: - The close project process is necessary for managing the contract and relationship between the buyer and seller 

Fady Sayah
by Fady Sayah , CMO , Digi Web LLC

A since for a project to be closed it has to be delivered from End to End 