Consider the project integration management knowledge area. Which of the following process are NOT included?

A. Integrated change control B. Develop project management plan C. Develop preliminary project scope statement D. Direct and manage execution E. None of the choices are true

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/01/09
Mohammed shahvali shaik
by Mohammed shahvali shaik , IT Manager , ARIG

All given process are included because point C is tricky because if we remove word prelimanary then Project scope statement is actually under Develop project management plan process. 

abdulla shutnawy
by abdulla shutnawy , Security Manager , nokia

Seven processes of project integration management :

Develop the project charter.

 Develop the project management plan.

Direct and manage project work.

monitor and control project work

perform integrated control

close project or phase

so I said C is not included in the integration managment

 

 

Project Integration Management starts with developing Project Charter, then Develop Project Management Plan, Direct and Manage Project work, Manage Poject Knowledge, Monitor and Control Project work and Perform Integrated Change Control Process and the finally Close Project or Phase.

Option C is correct answer, there is no as such developement of Scope statement.

Nasiru Sani Ango
by Nasiru Sani Ango , monitoring and inspection , National youth service corps

E-None But implementing Business process Improvement

ahmed Fouad khalil Khalil
by ahmed Fouad khalil Khalil , Senior project engineer , Advanced Line Group (Construction)

C-Develop preliminary project scope statement 

is not included the correct is to develop a project charter,

The scope statement is part of the project plan 

othman othman
by othman othman , High School Teacher Design/IT , Kuwait Bilingual School 2

All are included. A & D fall under integrationB & C fall under Scope ManagementWhich are all required.

Binu Thomas
by Binu Thomas , Camp Manager , Hospitality Catering LLC

E. None of the choices are true

Mohammad Alshokan
by Mohammad Alshokan , Project Engineer , Saudi Aramco

C. Develop preliminary project scope statement

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Integrated change control --------------------