Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Project cost control includes all of the following EXCECPT?

A. Establish contingency reserves that allow for unplanned, but potentially required, changes B. Inform stakeholders of approved changes C. Recording all changes to the cost baseline D. Influencing factors that create changes to the baseline E. Bringing expected cost overruns within acceptable limits

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/01/16
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. Establish contingency reserves that allow for unplanned, but potentially required, changes

More Questions Like This