Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

With respect to value analysis which of the following is the portion of the approved cost estimate ?

that has been budgeted for an activity during a certain time period? A. Actual cost (AC) B. Planned value (PV) C. Cost variance (CV) D. Earned value (EV)

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/01/23
Amir Abd Elaziz Ismail Almadlawy
by Amir Abd Elaziz Ismail Almadlawy , Shief accountant , Al sayeed sofee office

( B ) Planned Value ......................

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Planned value (PV) ----------------

More Questions Like This