your project team has already created the WBS, developed estimates for work packages, and sequenced the project activities using the arrow diagramming method. In addition, your team has applied schedule network analysis techniques to create the project schedule. Which action should be performed NEXT? A. Obtain acceptance of completed project scope B. Initiate schedule change control C. Decompose the work packages into smaller components called schedule activities D. Develop activity resource requirements E. Obtain approval of schedule
Answer D
Develope activity resource requirments
E. Obtain approval of schedule -------