to the planned scheduled activities, instead of managing the total float of network paths? A. Monte Carlo analysis B. Variance analysis C. Critical path method D. What-if scenario analysis E. Critical chain method
1) Monte Carlo analysis. 2) Variance analysis. 3) Critical path method.
This will be according to the budget and time frame.
E. Critical chain method ----------------