regulations mandated by the Sarbanes-Oxley act your company's upper management has tasked you with securing the company's network infrastructure. You have just completed the Develop Preliminary Project Scope Statement process. However, upon review you have determined that the resulting Preliminary Project Scope Statement is ambiguous and poorly written. A poorly written Preliminary Project Scope Statement will directly impact all of the following subsequent processes EXCEPT: A. Scope planning B. Scope verification C. Scope definition D. Develop project management plan
B. Scope verification -------------