Which of the following process takes the activities that are defined in the WBS and activity list, and accesses the amount ?

of time required to complete these activities? A. Schedule development B. Activity duration estimation C. Activity sequencing D. Activity definition

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/02/06
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Activity duration estimation ----------