Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following is the BEST candidate for a three-point estimate?

A. A brief schedule activity that takes a couple of hours B. A schedule activity with a considerable variation C. A schedule activity with a fixed duration D. A schedule activity with little duration variation

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/06
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. A schedule activity with a considerable variation