Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are in the process of controlling changes to a project baseline. Which of the following is the LEAST helpful input?

A. Cost baseline B. Work performance information C. Project funding requirements D. Performance reports E. Activity cost estimates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/13
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Activity cost estimates ---------------

More Questions Like This