All of the following statements regarding Control Accounts are true EXCEPT: ?

A. Each work package/ planning package may be associated with only one control account B. None of the choices are correct C. Control accounts are also referred to as cost accounts

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/13
Abdul Haseeb Gul
by Abdul Haseeb Gul , Accountant , Loafology cafe and Bakery

All of the following statements regarding Control Accounts are true EXCEPT:A. A control account is an assigned WBS level used to monitor cost and schedule performance of significant element of work.B. Control accounts are also referred to as cost accountsC. None of the choices are correctD. A control account is a management control point for cost summarization, scope description, and variance analysis and reporting.E. Each work package/ planning package may be associated with only one control account

irfan ali
by irfan ali , Internal Auditor , PYROCHEM (PVT) LTD (Manufacturing Concern) – Lahore, Pakistan

B because Control Accounts may referred to any account, mean any account ledger may be defined as control account...

Aijaz Soomro
by Aijaz Soomro , FINANCE MANAGER , SAMI FOUNDATION

The statement that is not true is A. "Each work package/planning package may be associated with only one control account." This statement is incorrect because a work package or planning package can be associated with multiple control accounts.

Adnan Saeed
by Adnan Saeed , Accounts Executive , HOUSE BUILDING FINANCE

A. Planning packages reflect a future segment of work within a control account that has not yet been decomposed into detailed work packages B. A control account is an assigned WBS level used to monitor cost and schedule performance of significant element of work C. As work becomes more clearly defined, planning packages are converted into work packages D. Each work package / planning package may be associated with only one control account E. Control accounts and planning packages are tools / techniques of activity definition process

Md Azimuddin
by Md Azimuddin , Senior Consultant , Subex

B. None of the choices are correct.

This statement is false as it is not accurate. The other statements are true:

Mohammad Sadre Alam Ansari
by Mohammad Sadre Alam Ansari , Materials Control Specialist , Dyncorp International - Afghanistan

E. Control accounts and planning packages are tools / techniques of activity definition process.

Stanley Mwangi  Stanley
by Stanley Mwangi Stanley , Procurement Officer , Ziara

C. Control accounts are also referred to as cost accounts

Anik  Chowdhury
by Anik Chowdhury , Accounts Officer , Maa Enterprise

A. Each work package/ planning package may be associated with only one control account

Anna Spivak
by Anna Spivak , Compliance Executive (Manager) , LALIRA DMCC (QIWI plc - subsidiary in Dubai)

Correct answer is A. Work packages are connected to one control account but cannot be connected to more than 1 control account. The control account will have few work packages

Ahmad Mekkawi
by Ahmad Mekkawi , Administrative and Call Quality Specialist , Integrated Transport Center

A. Each work package/planning package may be associated with only one control account.

In project management, multiple work packages or planning packages can be associated with a single control account, especially when the work is closely related or falls under the same control account for monitoring purposes.

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. None of the choices are correct