All of the following can be used to estimate the contingency reserves during Activity Duration Estimation EXCEPT: ?

A. Fixed number of work periods B. Quantitative schedule risk analysis C. Percentage of estimated activity duration D. Dependency determination

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/28
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Dependency determination -----------------