The project management executing processes include all of the following EXCEPT: ?

A. Information distribution, request seller responses B. Request seller responses, risk identification C. Select seller, acquire project team D. Perform quality assurance, develop project team

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/03/28
Bharat Chaudhari
by Bharat Chaudhari , Project Director , M/s. Al Zarraq Trad. Ent. LLC

B. Request seller responses, risk identification