Register now or log in to join your professional community.
A. Approved defect repair are input to the Direct and Manage Execution process and consists of documented, authorized requests for product correction of a defect found during quality inspection B. Approved change requests are input to the Direct and Manage Execution process and consists of documented, authorized directions that reduce the probability of negative consequences associated with project risks C. Approved corrective actions are input to the Direct and Manage Execution process and consists of documented, authorized directions required to bring expected future project performance into conformance with project plan D. Validated defect repair are input to the Direct and Manage Execution process and consists of notification that re-inspected repaired items have been either rejected or accepted E. None of the statements are false
B. Approved change requests are input to the Direct and Manage Execution process and consists of documented, authorized directions that reduce the probability of negative consequences associated with project risks