Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are in the process of analyzing activity sequence, durations, resource requirement, and schedule constraints in order to c?

reate the project schedule. Which of the following is least helpful input in this process? A. Activity duration estimates, risk register B. Project scope statements, activity list C. Schedule baseline, performance reports D. Activity resource requirement, resource calendars E. Activity attributes, project schedule network diagram

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/04/04
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Schedule baseline, performance reports 

More Questions Like This

Do you need help in adding the right keywords to your CV? Let our CV writing experts help you.