Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

You are the project manger assigned to build the house. You have determined the dependencies between activities on the project. ?

One of the activity dependencies is that the foundation of the house must be created prior to the construction of the frame which of the following is true? A. This is start-to-finish relationship B. This is an example of mandatory dependency C. This is an example of preferential logic D. This is start-to-start relationship E. This is finish-to-finish relationship

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/04/17
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. This is an example of mandatory dependency 

More Questions Like This