As software development can be very chaotic, your company has elected to follow the more rigorous approach to software development. Specifically, your company has chosen to adopt the Rational Unified Process (RUP) for your current software project. The RUP methodology is highly iterative and produces numerous deliverables include UML diagrams, architecture diagrams, prototypes, and test-cases. You have just produced your activity duration estimates and updated your activity attributes. Which process have you just finished? A. Schedule development B. Activity sequencing C. Activity duration estimation D. Activity definition
C. Activity duration estimation -------------------