You are in the process of controlling changes to the project scope. All of the following are outputs of this process EXCEPT: ?

A. Requested changes B. Project management plan updates C. Recommended corrective actions D. Work performance information E. Scope baseline updates

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/04/24
Mohamed Saber
by Mohamed Saber , Production Manager , AL-BLAGHA INDUSTRIAL COMPANY ( DAMMAM SHIPYARD )

A                                 requested changes

Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Work performance information 