Register now or log in to join your professional community.
to the planned scheduled activities, instead of managing the total float of network paths? A. Monte Carlo analysis B. Variance analysis C. Critical path method D. What-if scenario analysis E. Critical chain meth
to the planned scheduled activities, instead of managing the total float of network paths?
B. Variance analysis
E. Critical Chain method as the resources applied
E. Critical chain method ----------------------