You are in the process of developing an approximation of the costs of the resources needed to complete each schedule activity.?

All of the following are tools/ techniques you can use in this process EXCEPT: A. Analogous estimation, bottom-up estimation, parametric estimation B. Vendor bid analysis, reserve analysis C. Cost of quality, project management software D. Determine resource cost rate E. Cost aggregation

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/08
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Cost aggregation -------------------