A. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of monitor and control project work process B. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are inputs of integrated change control process C. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of integrated change control process D. None of the choices are correct

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/15
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Recommended corrective actions, recommended corrective actions, and recommended defect repairs are outputs of integrated change control proce