You are the project manager responsible for developing a new hybrid engine for a major auto manufacturer. You are in the process ?

of developing the project schedule and would like to identify the project risks and associated risk response plans. Where would you be able to retrieve this information? A. Organizational process assets B. Project scope statement C. Activity list D. Risk attributes E. Project management plan

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/15
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Project management plan -----------------