Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the statements regarding the WBS is FALSE?

A. The work activity is the lowest level of the WBS and is the point at which the cost and schedule for the work can be reliably estimated B. Different deliverables in the WBS can have different level of decomposition C. A WBS from a previous project can often be used as a template for a new project D. To identify the major deliverables of the project requires analyzing the detailed project scope statement E. The WBS is an output of the create WBS process

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/05/22
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. The work activity is the lowest level of the WBS and is the point at which the cost and schedule for the work can be reliably estimated