Which of the following best describes the calculations of late finish dates and late start dates for the uncompleted ?

portions of all network activities? A. Baseline B. Backward pass C. Forward pass D. Schedule variance E. Precedence diagramming method

user-image
Question added by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date Posted: 2019/06/12
Muhammad Farooq
by Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

B. Backward pass -----------------