Which of the following statements regarding WBS are FALSE?

A. The WBS is used to show which work components have been assigned to which organizational units. B. Each item in the WBS is generally assigned a unique identifier that can provide a means to track costs and resources C. The WBS is an output of the Create WBS process D. The WBS is deliverable-oriented grouping of project components that define the total scope of project

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2019/06/19
Muhammad Farooq
by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. The WBS is used to show which work components have been assigned to which organizational units.