Register now or log in to join your professional community.
preparation for upcoming Olympics. Construction begins on a project over a year ago. Stakeholders of the project want a status report on the performance of the project to the date. Unfortunately you are afraid to tell stakeholder that project is coming in significantly behind schedule. In fact schedule delays are so severe that the rebaselining of the project is required. Which of the following statements are true? A. None of the statement are correct B. Historical data are preserved when you rebaseline the schedule C. Approval from all stakeholder is required prior to rebaseline the schedule D. Rebaselining should be a normal mode of controlling the schedule E. Resource leveling techniques should not be used to rebaseline the schedule
A. None of the statement are correct