Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the initial setting timing of concrete?

user-image
Question added by Deleted user
Date Posted: 2019/07/18
Rajesh Gulabani
by Rajesh Gulabani , Senior Cost Manager , Neyo India Ltd

Initial setting time of Concrete depends on the type of Cement used, like for Ordinary Portland Cement (OPC) Initial setting time, is 30 Minutes. Whereas, for concrete setting time depends upon the Admixtures added in Concrete. Usually, it's preferred that concrete should be laid within 3 Hours of it's dispatch from Concrete mixer or Concrete plant, because the hydraulic (Chemical) reaction between CaO (Calcium oxide) and H2O (Water) starts. Thus, any sort of delay will affect workability and Compressive strength.