Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What is the acceptence time to remove formwork after casted concrete for columns, beams and slab? If you have reference please mention it?

user-image
Question added by Mohamed Sulaiman , Site Project Manager , Al tabarak for Engineering & Contracting company
Date Posted: 2013/12/19
محمد فهيم على عمارة عمارة
by محمد فهيم على عمارة عمارة , junior structural engineer , khatib & Alami CEC

according to ecp2003 for colums after48 hours and for side form work for slab and beams for48 hours but for bottom form work after time equal  teo times maximum span + two days

Deleted user
by Deleted user

My friend, your question is little open ended,  not knowing the type of cement you are using (SRPC or just standard Portland cement),

I will comment as follow; assuming a standard PC is being used  strike vertical formwork (columns and walls structures) after12 to18 hours, where as props to beams strike formwork after14 to21 days, good-luck

Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

It depends on the mixture of the concrete and climate, but normaly5-7 days, leevae some supports to keep out creep.

if slab lengthm (x2)+3 no its not right answer max concrete strength will get in days then only v remove

vivek dubey
by vivek dubey , Resident Engineer , Project & Development India Limited

normally it will take7 days as per IS.

MUHAMMAD YASIR BAIG
by MUHAMMAD YASIR BAIG , Civil Project Engineer , Urbacon Trading and Contracting (UCC)

Columns and shear walls means vertical elements form work we cane remove after24 hours but slab form work depend on span same like this(L*2+3) L=Maximum length of span

exp:

We have max span is9 m

9*2+3=21

Remove form work also depend on type of cement which one we use ...Best of luck

Abrar Hussain
by Abrar Hussain , Contract Manager , Sahara Tamiratt

It deepends upon the Concrete Design and Cement recommended. 

Generally using OPC for Grade10 ,15 &20 Cement Concrete recommended time for removal of form work is

For vetically supported form works in Beam, Columns & walls24 hrs.

Bottom supported formwork for Beams & Slabs min14 days Max21 days 

hassan amer ali algaifi
by hassan amer ali algaifi , مهندس مشروع , مؤسئسة علي الحصان للمقاولات

actually, there is a  different to remove formwork after casting between column and slab or beam in terms or time.

in terms of column , comperssive trength of concrete is not important to remove formwork, it means we can remove it after fainal setting time which is arround10 houres.

on other hand , to remove formwork for slab and beam, compressive strength is important .

for example, if we can get compressive strength requird after one week, it is ok.

faizel hussain nizar mohammed
by faizel hussain nizar mohammed , Data Warehousing Manager , GULF OFFICE SOLUTIONS

the curing period is12 to15 days but u can do shuttering and reiforcement works above a column casted on the previous day by giving enoug support and dont forget to give enoug water to the column casted.for beams and slabs dont remome before10 days without giving proper support

IHSAN ULLAH
by IHSAN ULLAH , Quantity Surveyor , AL-RASHID TRADING & CONTRACTION CO. (RTCC)

What is Acceptable time to remove formwork after pouring concrete for column

 

farzouq sadiq
by farzouq sadiq , Civil Engineer , Hyder and Sulaiman Elkhereiji Engineering Consultant

Walls, columns and vertical sides of beams to hours as may be decided by the engineer in charge Slabs (props left under)3 days Beam soffits (props left under)7 days Removal pr props to slabs

(a)  Spanning upto4.5 m

 

(b)  Spanning over4.5 m

7 days

 

days

Removal of props to beams and arches(a)  Spanning upto6 m

 

(b)  Spanning over6 m

days