If you have a concrete raft 1600 m3 , and you dont have enough shuttering to cast it one time , what are your recommendations?

user-image
Question added by Mohamed Sulaiman , Site Project Manager , Al tabarak for Engineering & Contracting company
Date Posted: 2013/12/31
Wolf Klaas Kinsbergen
by Wolf Klaas Kinsbergen , Managing Director, Designer , ingenieursbureau KB International NV

improvise with extra wood shuttering

G S
by G S , Senior lawyer , National Union of Attorney at Law of Romania

Pump-in through the narrow shutter self-compacting concrete.

AMIR RAMAY
by AMIR RAMAY , Project Manager , Bahria Town ( Pvt ) Ltd.

Complete the Concrete Pouring in  more than2 parts. provide Typical Construction Joints.