in Ms-Project, an activity duration can be split into several steps (Eg: while planning an activity for8 few weeks0-2 weeks work in progress,2-3 no work &3-5 work. how can be hide/ split the activity for a few)

user-image
Question added by Abdullah Thajudeen , Planning Engineer , Sustainable Builders
Date Posted: 2014/01/08
Kamran Umar
by Kamran Umar , PUBLIC RELATIONSHIP , CDGK

yes is there, show sub acitivity of split acivity

Ahmed Aboelazm
by Ahmed Aboelazm , Project Controls Lead / Project Manager , Nahaz Investment

you can use the steps option in the activity details tab