Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Padding is a common error in Project Management Do you or your team use padding when estimate activity duration or cost to prepare your schedule?why?

Padding is extra time or cost added to an estimate because the estimator does not have enough information

user-image
Question added by Wasim Khalil Mustafa Ali PMP® , Consultant , Malomatia
Date Posted: 2014/02/25
Mohammad Tohamy Hussein Hussein
by Mohammad Tohamy Hussein Hussein , Chief Executive Officer & ERP Architect , Egyptian Software Group

I do that sometimes only to mitigate identified posible risks.

Ahamed Shareef
by Ahamed Shareef , Divisional Head - Quality Assurance , Apollo Tyres Ltd

I have not used this concept

Raafat Sallam
by Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

according to the amout of uncertainty, then we can decide to use padding or not.

if there is a little amount of uncertainty, then no need for padding.

Mahmoud Abdulkader    Darwish
by Mahmoud Abdulkader Darwish , Consultant Bridge Engineer , Brench IDS consulting company

my answer is the same answer of  eng. Mohammad tohamy hussein-hussein

Raouf Borni
by Raouf Borni , QA Manager , Obeikan Folding Company

I do as safety tools, to tolerate my expectations and deadlines.

 

Daranivasan Anandaraman
by Daranivasan Anandaraman , Business Analyst , ADP

I create3 times and maintain3 records for each project seperately.

 

I follow guesstimates

- Identify3 values for each task in the WBS. Optimistic, pessimistic and most-likely time (Optimistic and pessimistic time will have2%-20% of chances of happening depending on the industry strength in that project. Bid manager/Estimator should know this tolerance level)

- Once identified, identify the Time expected as [(optimistic+(4*mostlikely)+pessimistic)/6] for each task

- Identify the variance expected as [square of ((pessimistic-optimistic)/6)] for each task

- Identify the standard deviation as [square root (variance expected)] for each task (Solution would be +or- some number)

 

Time for team = (Time Expected - Standard Deviation)

Time for management & for original record purpose = (Time expected)

Time for clients = (Time Expected + Standard Deviation)

 

This has helped me win projects and complete projects safely within time. Worked completely well upto projects worth around USD0.5M.

Amer Alokeh
by Amer Alokeh , Service Delivery Manager , SmartWorld DWC LLC

If you are adding extra time or cost to an activity to mitigate identified risk then this is called Contingency Reserve and not padding.

Following a proper risk management process will assign required reserves to these activities instead of following this unprofessional habit.

 

 

More Questions Like This