thank you for invited
i am with mr fredy's answer
According to PMBOK5th edition, there are10 Knowlegde areas:
1- Project Integration Management
2- Project Scope Management
3- Project Time Management
4- Project Cost Management
5- Project Quality Management
6- Project Human Resources Management
7- Project Communications Management
8- Project Risk Management
9- Project Procurement Management
10- Project Stakeholder Management
The new knowledge area is the last one, Project Stakeholder Management. Actually, the Project Communications Management has been separated into Project Communications Management and Project Stakeholder Management.
Time.
Quality.
Cost.
Scope.
Risk.
Procurement.
Integration.
Communication.
HR.
Now they became12 areas.
With Mr. Antonio, it becomes10 (TEN) Knowledge areas, by adding:
Project Stakeholder Management.
I belive that you mean PMI Project Management Knowledge areas.
Acorrding to PMBOK fourth edition there was a9 knowledge areas ( Integration Management –Project Scope Management - Project Time Management - Project Cost Management -Project Quality Management - Project Human Resource Management -Project Communications Management - Project Risk Management -Project Procurement Management )
In the PMBOK fifth edition PMI added another knowledge called Project Stakeholder Management.
For more details about project management PMI project management project management processes, process groups and knowledge areas please refer to PMI-PMBOK.
To my knowledge, the9 areas in PMP processes are still, project scope management, project integration management, cost management, communication management, time management, quality management, HR management, risk management, & procurment management.
If change management is not part of the risk management, I would like to add that one, if I may.
Dear Mr. Labib,
can you please illistrate the3 extra areas other than the9 commen areas?
thanks in advance.