Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Authoritative or Participative?

A budget maker interviews the manger of firm's mobile line and the mobile parts assembling machine operators. The objective is to define a cost standard that each of these parties belives is the best result that could be achieved assiming that nothign went wrong. What sort of Standard is being set? A. Authoritative Ideal Standard B. Participative Ideal Standard C. Authoritative currently attainable standard D. Participative currently attainable standard

user-image
Question added by Anayatullah Tahir , Finance Manager , Etqan Projects
Date Posted: 2014/03/16
Zohaib Ahmed
by Zohaib Ahmed , Chief Accountant , VECTRUS

A. Authoritative Ideal Standard

More Questions Like This