During which project management process group is rough order of magnitude estimate made?

user-image
Question added by Ghada Sameer , Project Manager and media executive , CQA
Date Posted: 2014/03/20
Abdul-Hameed Deeb Al-Sawadi
by Abdul-Hameed Deeb Al-Sawadi , IT Manager , Masaneed Commercial Group (MCG)

A rough order of magnitude (ROM) estimate takes place very early in a project’s life cycle — during the project selection and approval period and prior to project initiation in most cases.  The main purpose of the ROM estimate is to provide decision-makers with the information necessary to make a decision on whether it makes sense to move forward with the project based on the estimated level of effort, in terms of completion time and cost. 