Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

TOTAL FLOAT goes wrong in on computer to another for the same program

Let's say for an example i have an activity that is critical and it is delayed - it shows in a different computer (after exporting and importing the program) that it has a total float of +VE10 days which is not right. HOW CAN I FIX THIS?

user-image
Question added by Kareem Mohammed Khattab , Planning Manager , ZAID ALHUSSAIN & BROTHERS GROUP
Date Posted: 2014/04/20
Hassan SAFAR
by Hassan SAFAR , Planning Manager , Bilfinger

mainly when you export the xer file, it should be a full package. the main issue that most of planners are facing is the out of sequence activities (logic). the out of sequence activities should be checked and rectified on every run

Mohammed Abdul Hannan
by Mohammed Abdul Hannan , Planning Manager , North 25 (Subsidary of Dubai Holding & Meraas)

The best way is apply the must finish by constraint and the float gets automatically adjusted.

If not check the calendars.

Shady Shoukry
by Shady Shoukry , Planning Team Leader , Arabian Construction Company - ACC

Just export your calender and your view and inport them in the other computer. then run schedule and u'll find them as they should be. 

Note : oracle Primavera is not like Database Primavera , no way they could be the same

Muhammad Danish Habib
by Muhammad Danish Habib , Cost and Schedule Engineer , Manitoba Hydro

Yes the major issue can be calander or if you are importing with the option of update exisiting than may be there is some logical issue.

Binil Paul
by Binil Paul , Sr. Planning Engineer , KEO International Consultants

Calendar and holidays were not exported or imported

units arent the same in both

finish dates and data dates may be different in both PC

Asif Muhammad
by Asif Muhammad , SR. Planning Engineer , CATIC - The Chinese Company

There may-be numerous reasons likely,

a)     Time units should be defined properly in all computers e.g. Hours / (Day, Week, Month & Year)

b)    Same Calendar should be defined properly on all computers e.g. Working hours and vacations

Ali Slim
by Ali Slim , Central Supply Technician Supervisor , Mohamad Slim Establishment

I do not think so, it must be the same.

More Questions Like This