Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

What are the fastest methods for changing the Activities ID in P6?

user-image
Question added by Asif Muhammad , SR. Planning Engineer , CATIC - The Chinese Company
Date Posted: 2014/04/28
Mohammed Abdul Hannan
by Mohammed Abdul Hannan , Planning Manager , North 25 (Subsidary of Dubai Holding & Meraas)

It can be done through Global change using strings method

Hassan SAFAR
by Hassan SAFAR , Planning Manager , Bilfinger

Activity ID should not be change. you have to fix the logic from the very beginning. In some urgent case, if you want to change you may use global change option.

Mubarak Awad
by Mubarak Awad , مهندس مشرف على مشاريع السيول وشبكة تخفيض منسوب المياه الجوفية , WSP

Of accredited English language courses from accredited training centers

The fastest way to learn a language is to be surrounded by it. Being immersed in a society where that language is spoken will force an individual to interact with others in their native tongue; allowing for plenty of practice.

Salman Zahoor
by Salman Zahoor , Data Entry Operator , Quick Book School

The fastest method is to create penllaity with referance of existing person

Nelson Pate
by Nelson Pate , Civil Structural Engineer , Astad Project Management

Staudy and practice among the people speaking the said language.

Shady Shoukry
by Shady Shoukry , Planning Team Leader , Arabian Construction Company - ACC

Change one ID then select all and Fill Down fastest way but not right coze every project must have it's ID

another one b4 starting project General menu then Change the ID from the Botton

Farid Arab
by Farid Arab , Senior Planning Manager , Kleindienst Group - THOE limited

Can you explain your problem further? there are many methods for changing the activity ID's quickly.

I can help if I know how yout want the Activity ID's look like

Kishore A Nair
by Kishore A Nair , Planning Engineer , KAD CONSTRUCTION L.L.C

Activity-ID sequence decision is one among and the first consideration required area before starting with your activity adddition. I would like to suggest a few things  which I felt it to be considered in your future plans .

 

 When you create activity-id always give the first2 or3 places as characters and these should be common through out the project.

eg. say you have2 zones - Z1 & Z3 . Then start it with like this " Z1CO------- " . So when you planned your ID in this manner later on  changing the same or converting same will be easy.  

When you want to change a set of Z1 activities to Z3 . Then its simple select all and go with  the replace option and apply replace it with Z3. So your ID will be changed easily to Z3.

And if you want to copy paste and to create a new section then also its simple . Do the copy paste option select the3 rd option replace the2 characters with Z3. So in this manner you can create a new section easily.

 

You can change anything in one shot in P6 other than the Activity-ID. Because ID option is unique and all your data base options in the program are refered to the ID what you are giving in the program. 

Hope it will help you.

 

Muhammad Ali Khan
by Muhammad Ali Khan , Proposals Engineer , Enerflex Middle east

Select all the activities and then right click and use "Renumber activity IDs" Command

Muhammad Danish Habib
by Muhammad Danish Habib , Cost and Schedule Engineer , Manitoba Hydro

Use Renumber Activity ID option under EDIT menu

More Questions Like This