Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

Which of the following can be used to determine what work is included in each work package for each of your team members?

A. None of the choices are correct B. WBS dictionary C. RBS D. Project scope statement E. Project schedule

user-image
Question added by Ghassan Jaradat , Projects Manager , ITAC Information Technology and Automation Company
Date Posted: 2014/05/20
ABU SAIF MOHAMMAD MAHIN, PMP
by ABU SAIF MOHAMMAD MAHIN, PMP , Head of Design and Production Engineering, Financials Solutions , Southtech Limited

B. WBS dictionary 

More Questions Like This