Ask the Community
Ask any professional question and get answers from other specialists.
A. The level of effort of a task B. When a task starts and stops C. How tasks are related to each other D. Who is assigned to what task E. All of the above.
Option B - Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary ... See More
B. because a gantt chart is a useful graphical tool which shows activities or task performed against time
Answer: BExplanation: Section: (none) Reference: Rita says that a Gantt chart in its purest form does not show task interdependencies. That would make B correct. (in seco ... See More
I will try to make it few words :) 1. add another column to your data which should have a formula to calculate the task period 2. then you should have a start point for ... See More