Trending Planning and scheduling Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Labeb Ahmed's image
Question added by Labeb Ahmed Senior Planning Engineer Saudi Baytur Company
7 years ago
Answers:
13
Followers:
Views:
897
Vote Count:
2
Answer should contain a minimum of 25 characters.
Ahmed Khater's image
Question added by Ahmed Khater ID& Fit- Out Construction Manager Harmony Atelier Interior Design& Decoration
8 years ago
Answers:
2
Followers:
Views:
225
Vote Count:
0
Answer should contain a minimum of 25 characters.
Christian Festus's image
Question added by Christian Festus Supervisor Al Marina Trading, Contracting & Construction Co.
10 years ago
Answers:
1
Followers:
Views:
115
Vote Count:
1
Answer should contain a minimum of 25 characters.
Default profile image
Question added by Amjad Fraz Manager of Projects Al Nafisi Group - Kuwait
10 years ago
Answers:
6
Followers:
Views:
72
Vote Count:
0
Answer should contain a minimum of 25 characters.
Ghaleb Sobh's image  
Answer added by  Ghaleb Sobh, Construction Manager , CCC
7 years ago

Most of projects willing to calculate the project progress based on the cost, as this is the way to measure the project revenue and the cash flow. However, I believe the ... See More

Sharafeldin Shehatah's image  
Answer added by  Sharafeldin Shehatah, Chief Executive Officer, Enforce Engineering Consultancy
7 years ago

 Cost or Man-hours is not an accurate way to measure the progress. The completion percentage of each task shall be measured by the quantity completed and approved by the ... See More

Muhammad Irfan Chughtai's image  
Answer added by  Muhammad Irfan Chughtai, IT Project Manager, Buzzeff Middle East
7 years ago

You select metric based on your required measurement.  1. In order to measure Schedule Progress you would use Man-hours. 2. In order to measure Cost efficiency on the pro ... See More

Zaferullah Sharief, PMP®'s image  
Answer added by  Zaferullah Sharief, PMP®, Project Manager, Huawei Technologies
8 years ago

PERT (Program Evaluation and Review Technique) is a technique for estimating that applies an average of optimistic, pessimistic and most likely estimates when there is ... See More

saad salem's image  
Answer added by  saad salem, Senior Civil/Structure Engineer ( Resident Engineer ), Dar Al Hanadasah Consultants
7 years ago

Work progress can be measured by cost of actual work done .

Joey Balanquit's image  
Answer added by  Joey Balanquit, Planning Engineer, Mott MacDonald
7 years ago

Both stands for different project progress perspective. Usually, if you are in contractor side primarily we are concern about cash flow, means from time to time we used t ... See More