Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

Product verification is usually performed in closing process. Which of the following statement are true? ‎

A. Product verification is used to verify that work was completed correctly and satisfactorily B. Product verification provides management with information how effectivel‎ ... See More

Answers:
1
Followers:
Views:
115
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
5 years ago

Contract documentation is an input to the Contract Closure process. What does the process consist of?‎

A. Approved change requests B. Supporting schedule C. Procurement audit documentation D. Warranties E. Payment records‎

Answers:
3
Followers:
Views:
144
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

You are managing a large construction project that's been broken down into sub-projects (or phases). ?‎

Each of these sub-projects is scheduled to take between three and six months to complete. At the end of each subproject, you plan to go through the closing processes and ‎ ... See More

Answers:
2
Followers:
Views:
318
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

Which of the following is the correct order of actions that you take during the Closing processes? ‎

A. Get formal acceptance, close the contract, write lessons learned, release the team B. Get formal acceptance, write lessons learned, release the team, close the contrac‎ ... See More

Answers:
1
Followers:
Views:
425
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

Your client has terminated your project before it is complete. Which of the following is true?‎

A. You must update the project management plan to reflect this change B. You must work with the team to document the lessons learned C. You must stop all work and release‎ ... See More

Answers:
2
Followers:
Views:
150
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

Your project team has completed the project work. All of the following must be done before the project can be closed EXCEPT:?‎

A. Make sure the scope of the project was completed B. Get formal acceptance of the deliverables from the customer C. Ensure that the schedule baseline has been updated D‎ ... See More

Answers:
6
Followers:
Views:
179
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

In which of the following types of organizational structures are the MOST anxiety experienced at project close-out?‎

 A. Weak matrix. B. Strong matrix. C. Functional. D. Projectized. E. Balanced matrix.‎

Answers:
2
Followers:
Views:
76
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago
Answers:
10
Followers:
Views:
1022
Vote Count:
2
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

The primary function of the Closing processes is to perform which of the following?‎

  A. Perform post-implementation audits to document project successes and failures. B. Formalize project completion and disseminate this information to project part‎ ... See More

Answers:
5
Followers:
Views:
346
Vote Count:
1
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

What type of organization experiences the least amount of stress during project closeout?‎

  A. Functional   B. Weak matrix C. Strong matrix D. Projectized‎

Answers:
8
Followers:
Views:
337
Vote Count:
1
Answer should contain a minimum of 25 characters.