Trending RFP Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

You are providing clarification to the prospective vendors, on the requirements prepared by you in the RFP for outsourcing a piece of work?‎

 You are in which part of procurement process? A.  Plan Procurement  B.  Conduct Procurement C.  Evaluate Proposal     D. Administer Procurement            ‎ ... See More

Answers:
9
Followers:
Views:
149
Vote Count:
1
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

You are project manager and now in middle of creating RFP(Request for proposal). RFP(Request for proposal) is done in _? ‎

  A. Plan Procurements B. Close Procurements C. Administer Procurements D. Conduct Procurements‎

Answers:
5
Followers:
Views:
272
Vote Count:
0
Answer should contain a minimum of 25 characters.
Ksenija Kancelak's image  
Answer added by  Ksenija Kancelak, Construction Project Manager, City of Koprivnica, Koprivnica (Croatia)
8 years ago

My opinion is that the right answer is: B. Conduct Procurement  

Ksenija Kancelak's image  
Answer added by  Ksenija Kancelak, Construction Project Manager, City of Koprivnica, Koprivnica (Croatia)
8 years ago

My opinion is that the right answer is: B. Conduct Procurement  

Ksenija Kancelak's image  
Answer added by  Ksenija Kancelak, Construction Project Manager, City of Koprivnica, Koprivnica (Croatia)
8 years ago

My opinion is that the right answer is: B. Conduct Procurement