Trending Schedule Analysis Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now.?‎

But at the latest status meeting, the team only reported that% of the work has actually been completed. The team has spent $, so far on the project. How would you BEST d‎ ... See More

Answers:
8
Followers:
Views:
48
Vote Count:
1
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago
Answers:
6
Followers:
Views:
1918
Vote Count:
4
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
11 years ago

What is Schedule Analysis? ‎

The complex business relationships characteristic and technology advancements of the modern construction industry, construction scheduling has become increasingly more im‎ ... See More

Answers:
10
Followers:
Views:
554
Vote Count:
14
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago
Answers:
7
Followers:
Views:
18
Vote Count:
3
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago

Comparing target dates with the actual or forecast start and finish dates is called?‎

A. Variance Analysis B. Earned Value C. Progress Reporting D. Crashing‎

Answers:
6
Followers:
Views:
17
Vote Count:
4
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
6 years ago

Certain resources have been added to tasks on the critical path so as to reduce the project duration. As a result the plan should then be reviewed?‎

for the:  A. Possible lag time on other paths. B. Resource assigned to other tasks on the critical path. C. The most time consuming task remaining in the plan. D. Emerge‎ ... See More

Answers:
7
Followers:
Views:
28
Vote Count:
0
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago
Answers:
5
Followers:
Views:
18
Vote Count:
3
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
11 years ago
Answers:
7
Followers:
Views:
216
Vote Count:
9
Answer should contain a minimum of 25 characters.
Tanveer Ahmad Niazi's image
Question added by Tanveer Ahmad Niazi CEO (Self-employed) Project Management Training & Consultant
11 years ago

What would be the best response if the Employer (Client) requests verbally for an additional work? Chose the options below and explain why?‎

Options -1. Accept that -2. Ask for a written request -3. Ask him to let you come back to him after getting feedback from management -4. Ask him to let you come back to h‎ ... See More

Answers:
8
Followers:
Views:
313
Vote Count:
9
Answer should contain a minimum of 25 characters.
Binil Paul's image
Question added by Binil Paul Sr. Planning Engineer KEO International Consultants
7 years ago
Answers:
1
Followers:
Views:
82
Vote Count:
1
Answer should contain a minimum of 25 characters.