Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago

Comparing target dates with the actual or forecast start and finish dates is called?‎

A. Variance Analysis B. Earned Value C. Progress Reporting D. Crashing‎

Answers:
6
Followers:
Views:
17
Vote Count:
4
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique? ‎

  A. Critical Path Method B. Schedule Compression C. Resource Leveling D. What if Analysis  ‎

Answers:
10
Followers:
Views:
801
Vote Count:
1
Answer should contain a minimum of 25 characters.
Muhammad Yuseef's image
Question added by Muhammad Yuseef IT Manager Master Point Trading
8 years ago
Answers:
8
Followers:
Views:
803
Vote Count:
2
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

The customer has demanded that you reduce the schedule by three weeks. What does this mean in terms of the Project schedule?‎

a. You have decided that fast tracking is the best option to pull in the schedule by three weeks b. You have decided that crashing the schedule is the best option to pul‎ ... See More

Answers:
7
Followers:
Views:
1367
Vote Count:
1
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

Management from the customer side wants to bring in a project one month earlier than they had...‎

originally planned. Based on the current project timeline, product testing will have to be cut short. You have reviewed several options with the customer; they have decid‎ ... See More

Answers:
3
Followers:
Views:
266
Vote Count:
1
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
7 years ago

You are project manager for a project. This project was originally scheduled for completion in 1 year but already 2 years over and now also project?‎

 is in execution phase. Which statement is TRUE about the project?  A. requirement added later therefore project is running late B. temporary project C. key resource h‎ ... See More

Answers:
7
Followers:
Views:
14
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

Which of the following statements are TRUE regarding various Activity Scheduling tools?‎

A. PDM allows for conditional branching and iteration of activitiesB. PDM uses activity-on-node (AON) diagramming method.C. PDM allows for conditional branching and itera‎ ... See More

Answers:
4
Followers:
Views:
646
Vote Count:
0
Answer should contain a minimum of 25 characters.
Muhammad Farooq's image
Question added by Muhammad Farooq QA-QC MANAGER AL Bawani contracting co.
8 years ago

CPI is 1.2, SPI is 1.1. Four months later CPI is.91 and SPI is .86. The most likely reason for this change is?‎

  a. The project manager has not been keeping track of variances on the project to implement corrections b. As work packages were being executed, discovery on critical ‎ ... See More

Answers:
7
Followers:
Views:
365
Vote Count:
0
Answer should contain a minimum of 25 characters.