Trending Staff Scheduling Discussions

Follow

Ask the Community


Ask any professional question and get answers from other specialists.

Stream language
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago

Should we revise the baseline schedule after approval of each project control change notice?‎

Some time a change notice is less value and some it is more value. When should we revise baseline schedule.‎

Answers:
7
Followers:
Views:
71
Vote Count:
3
Answer should contain a minimum of 25 characters.
ZULFIQAR ALI's image
Question added by ZULFIQAR ALI Planning/ Project Control Manager King Abdullah University Of Science And Technology
7 years ago

Should we revise the baseline schedule after approval of each project control change notice?‎

Some time a change notice is less value and some it is more value. When should we revise baseline schedule.‎

Answers:
7
Followers:
Views:
71
Vote Count:
3
Answer should contain a minimum of 25 characters.
Mike Emerson Pasaron's image
Question added by Mike Emerson Pasaron Safety Officer Arabian Petrochemical Co. (PETROKEMYA)
11 years ago
Answers:
3
Followers:
Views:
113
Vote Count:
0
Answer should contain a minimum of 25 characters.
Ahmed Elassar MCIArb BSc Eng's image  
Answer added by  Ahmed Elassar MCIArb BSc Eng, Senior Contract Engineer, Capital Projects Dep. of Qatar University
7 years ago

Revised shcedule mean that the change impacted on the BL Schedule and extension of time has been approved, in this case the answer of your question is YES

ZULFIQAR ALI's image  
Answer added by  ZULFIQAR ALI, Planning/ Project Control Manager , King Abdullah University Of Science And Technology
7 years ago

The following examples illustrate the varying contract conditions that define the need for a recovery schedule: • If the project falls behind schedule more than 14 days o ... See More

Default profile image  
Answer added by  Samar Abu Shaban , Regional HR Operations manager, souq.com
11 years ago

Fraud in the work place might happened and should be dealt with it in immediate action yet after have enough evidence; also, remember that you shouldn't be emotional ... See More

Default profile image  
Answer added by  Gandhi Mohankumar , Construction Project Manager, Golden Sand Engineering Construction
6 years ago

Revised schedule means, with reference to Baseline plan, a revised plan will be submitted to client for approval.

Noel Lane's image  
Answer added by  Noel Lane, Director of Operations, Integrated Building Company
7 years ago

Every schedule, just like every plan, requires constant monitoring and adjustment as situations and project development occurs. The original schedule is a baseline measur ... See More

Razi Ullah's image  
Answer added by  Razi Ullah, Senior Cost Engineer, Peace River Hydro Partners
7 years ago

After approval of any significant scope change which impacts the total duration of the project, the baseline schedule needs to be revised.