Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Multifunctional Project
The consultant representative PM could monitor a project constructed in many sites through :-
1- Progress reports delivered to him from the sites managers.
2- Monitoring the over all progress from the total project time frame schedule.
3- Progress meetings with the sites managers.
4- Periodical pre-schedule sites visit to ensure the site progress activities.
5- Monitoring the approved payment certificates against the progress percentage.