What is waste percentage taken into account when preparing material requirement in steel fabrication work for a particular job?

user-image
Question ajoutée par Ashfaq Hussain , Dy. Chief Engineer , MCC Resources Development co.
Date de publication: 2014/07/18
pon esakki
par pon esakki , Site Engineer , National contracting company limited

Below10% for structural fabrication

Below15% for Tank and vessel

Nadhem Jlali
par Nadhem Jlali , Draftsman steel construction Autocad ,doc controle register and planner technician o IBM Maximo , NLsupervision Tunisia company

 

the percentage of waste taken into account when preparing the material needs of manufacturing jobs in steel for a particular job is different from one domain to another, for example: * Metal structural work: - about 10% of dechet without permission splicing.                                          - About 5% to8% if the splicing is allowed. * Boiler:  - can reach up to20% of waste (tank, silo ...)

Ahmed Mahmoud Ali Mahmoud El-sayed
par Ahmed Mahmoud Ali Mahmoud El-sayed , Lead QA/QC Engineer , Elsewedy Electrical PSP

not less than15%

RIZWAN SHARIEF
par RIZWAN SHARIEF , project engineer , Al fanar ceramics

5-10% waste need to calculate for fabrication.