Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which is NOT an input to the Create WBS process?

Project Scope Statement Organizational Process Assets Scope Management Plan WBS Dictionary

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2014/08/27
طﻻل صدقي عثمان arman
par طﻻل صدقي عثمان arman , رئيس مجلس اﻹدارة والمدير العام , شركة عرمان للهندسة والمقاوﻻت المحدودة

WBS dictionary is not an input for Create WBS Process while the rest are ...

Salauddin Mohammad
par Salauddin Mohammad , Sr. Manager, Software Development , Aspen Technology Inc

WBS dictionary is the output of create WBS process, so my answer to your question is "WBS dictionary"..

Faraz Shafiuddin Shafiuddin
par Faraz Shafiuddin Shafiuddin , Business Analyst , National Guard Health

WBS Dictionary, as rest all are inputs, this is only a repository of terms and definitions and cannot be treated as a input.

Utilisateur supprimé
par Utilisateur supprimé

WBS Dictionary will not be a direct Input, however it can be used as reference.

hossam azzam
par hossam azzam , Fast food restaurant,s manager. , alexandria-egypt

WBS Dictionary

hatem labib
par hatem labib , Quality control manager , MISER consultant

WBS dictionary is output

Raafat Sallam
par Raafat Sallam , Organizational Development and Training Consultant , Training Centers, Marketing Organizations.

WBS dictionary is one of the output of create WBS process

Antonio J Pedreño Avila
par Antonio J Pedreño Avila , Project Manager , SEMI USA

WBS dictionary is one of the elements of the Scope Baseline therefore it is not an input, it is an output of the Create WBS process.

The Scope Baseline include:

1. Project Scope Statement

2. WBS

3. WBS dictionary

Mohamed Hamdy Kamal Riad
par Mohamed Hamdy Kamal Riad , Senior Solution Architect , IBM

Fourth option 

WBS Dictionary

SunilKumar N
par SunilKumar N , Senior Business Analyst / Project Manager , AlMusbah IT and Telecoms

The use of Work Break Down Structure (WBS) is bring down or breaking objects at atomic level and / or Managing Levels.

1) Project Scope Statement: This is used for breaking down scope.

2) Organizational Process Assets: In organisations the process tools, templates and key level documents which can be break down according to the project requirements.

3) Scope Management Plan: This is used to break down the scope at simple statement levels.

4) WBS Dictionary: This is a type of Glossary and /or Dictionary where concepts are already broke at atomic level. 

 

Conclusion: WBS Dictionary is a subset of Work Break Down Structure (WBS) hence this can't  be an input for WBS rest of all can be an Input.

Project Scope Management Plan is not an input to the WBS Creation process

More Questions Like This